|本期目录/Table of Contents|

[1]李元松1,吴春华2,段 鑫1,等.帷幕注浆工程质量模糊综合评价模型[J].武汉工程大学学报,2015,37(08):1-5.[doi:10. 3969/j. issn. 1674-2869. 2015. 08. 001]
 ,,et al.Fuzzy comprehensive evaluation model of grouting curtain engineering quality[J].Journal of Wuhan Institute of Technology,2015,37(08):1-5.[doi:10. 3969/j. issn. 1674-2869. 2015. 08. 001]
点击复制

帷幕注浆工程质量模糊综合评价模型(/HTML)
分享到:

《武汉工程大学学报》[ISSN:1674-2869/CN:42-1779/TQ]

卷:
37
期数:
2015年08期
页码:
1-5
栏目:
资源与土木工程
出版日期:
2015-08-31

文章信息/Info

Title:
Fuzzy comprehensive evaluation model of grouting curtain engineering quality
文章编号:
1674-2869( 2015)08-0001-05
作者:
李元松1吴春华2段 鑫1李 洋1董开源2
1.武汉工程大学资源土木工程学院,湖北 武汉430074;2.黄石市矿山安全检测检验所,湖北 黄石435000
Author(s):
LI Yuan-song1WU Chun-hai2DUAN Xin1LI Yang1DONG Kai-yuang2
1.School of Resource and Civil Engineering, Wuhan Institute of Technology, Wuhan 430074, China;2.Huangshi Institute of Mine Safety Inspection, Huangshi 435000, China
关键词:
岩溶矿床地下水防治帷幕注浆工程质量评价模型
Keywords:
Karst water-filled deposit groundwater blockage grouting curtain engineering qualityassessment model
分类号:
TU 443
DOI:
10. 3969/j. issn. 1674-2869. 2015. 08. 001
文献标志码:
A
摘要:
帷幕注浆工程质量验收指标与工作过程具有模糊性与不确定性,现有的单因素评价或多因素混合评价都难以给出定量结论,提出运用模糊综合评价方法. 基于模糊决策理论,尝试将帷幕注浆工程质量的影响因素进行分类并量化,根据专家经验与影响因子的特点,选用对应的隶属函数,应用层次分析法确定权重系数,建立帷幕注浆工程质量的定量评价模型,并将该模型用于大冶矿带3个典型岩溶矿床帷幕注浆堵水工程的质量评价与鉴定,结果与抽水试验和后期运营状态具有高度的一致性.
Abstract:
It is difficult to get the quantitative conclusion by the single factor evaluation and the multi-factor synthetic evaluation because the check indexes of curtain grouting engineering quality and the work processes have the characteristics of ambiguity and uncertainty. The method of fuzzy comprehensive evaluation was proposed. Based on fuzzy decision theory, factors influencing the quality of the curtain grouting engineering and water plugging effect evaluation were classified by analytic hierarchy process method to determine the weight coefficient, then a quantitative evaluation model of the curtain grouting engineering quality was built, which was used in evaluation and appraisal of quality in Daye ore with multiple typical karst deposit curtain grouting water plugging engineering, and the results are satisfactory.

参考文献/References:

[1] 高建军,祝瑞勤,徐大宽.岩溶充水矿床帷幕注浆堵水技术研究[J].水文地质工程地质, 2007(5):123-127.GAO Jianjun,ZHU Ruiqin,XU Dakuan. Re-discussion on plugging technique with curtain grouting in karst water filled ore deposits[J]. Hydrogeology&Engineering Geology, 2007(5):123-127.(in chinese)[2] 祝世平,王伏春,曾夏生.大红山矿帷幕注浆治水工程及其评价[J]. 金属矿山,2007(9):79-83.ZHU Shiping, WANG Fuchun, ZENG Xiasheng. Groundwater blockage by grouting curtain in Dahongshan mine and its evaluation[J].Metal Mine,2007(9):79-83.(in Chinese)[3] 韩贵雷,于同超,刘殿凤,等. 矿山帷幕注浆方案研究及堵水效果综合分析[J].矿业研究与开发,2010, 30(3):95-98.HAN Guilei,YU Tongchao,LIU Dianfeng,et al. Study on curtain grouting scheme and comprehensive analysis on its water plugging effection in zhongguan ironmine[J]. Mining R&D,2010,30(6):95-98.(in Chinese)[4] 陈静,王军. 岩溶矿区帷幕注浆截流效果的抽水试验法评价[J].采矿技术,2008,8(6):53-55.CHEN Jing, WANG Jun.The effect evaluation of water prevention after curtain grouting engineering in karst mine area using pumping test[J]. Mining Technology, 2008, 8(6): 53-55.(in Chinese)[5] 杨米加, 陈明雄, 贺永年. 注浆理论的研究现状与发展方向[ J] . 岩石力学与工程学报, 2001,20(6): 839-841.YANG Mijia,CHEN Minxiong,HE Yongnian. Current research state of grouting technology and its development direction in future[J]. Chinese Journal of Rock Mechanics and Engineering,2001,20(6):839-841.(in Chinese)[6] 张志沛,刘旭,徐汉民,等. 煤矿采空区注浆工程质量检测的试验研究[J]. 岩土工程学报,2005, 27 (5):604-606.ZHANG Zhipei, LIU Xu, XU Hanmin. Experimental studies on grouting quality examination of gob of coalmine[J]. Chinese Journal of Geotechnical Engineering, 2005, 27 (5):604-606. (in Chinese)[7] 李术才,张霄. 地下工程涌突水注浆止水浆液扩散机制和封堵方法研究[J]. 岩石力学与工程学报,2011, 30(12): 2378-2395.LI Shucai,ZHANG Xiao. Research on mechanism of grout diffusion of dynamic grouting and plugging method in water inrush of underground engineering[J]. Chinese Journal of Rock Mechanics and Engineering, 2011, 30(12): 2378~2395.(in Chinese)[8] 张国立,张辉,孔倩.模糊数学基础及应用[M].北京:化学工业出版社,2011:9.ZHANG Guli, ZHONG Hui,KONG Qian.Fuzzy mathematics foundation and its application[M]. Beijing: Chemical Industry Press, 2011:9.(in Chinese)[9] 李元松,陈文峰,李新平.基于模糊神经网络的边坡稳定性评价方法[J].武汉理工大学学报,2013, 35(1): 113-118.LI Yuansong,CHEN Wenfeng,LI Xinping.Satbility assessment of rock slope based on Fuzzy neural network[J].Journal of Wuhan University of Technology,2013, 35(1):113-118.(in Chinese)[10] 吴茂民.边坡失稳灾害的模糊综合评估技术及其应用[D].福州:福州大学,2005.WU Maomin.Fuzzy synthetic assessment on disaster of slope instability and its application[D]. Fuzhou:Fuzhou University,2005.(in Chinese)[11] 黄建文,李建林,周宜红.基于AHP的模糊评判法在边坡稳定性评价中的应用[J].岩石力学与工程学报,2007,7 (增刊):2627-2632.HUANG Jianwen,LI Jianlin,ZHOU Yihong.Application of Fuzzy analysis based on AHP to slope stability evalution[J]. Chinese Journal of Rock Mechanics and Engineering,2007,7(suupl.):2627-2632.(in Chinese)

相似文献/References:

[1]李元松1,吴春华2,段 鑫1,等.大志山注浆帷幕防治水工程大型抽水试验[J].武汉工程大学学报,2015,37(08):6.[doi:10. 3969/j. issn. 1674-2869. 2015. 08. 002]
 ,,et al.Steady-flow pumping test of groundwater blockage by grouting curtain in Dazhishan mine[J].Journal of Wuhan Institute of Technology,2015,37(08):6.[doi:10. 3969/j. issn. 1674-2869. 2015. 08. 002]

备注/Memo

备注/Memo:
收稿日期:2015-04-30作者简介:李元松(1964-),男,湖北应城人,教授,博士. 研究方向:岩土工程领域的教学与研究工作.
更新日期/Last Update: 2015-08-29